General Update on Site works at 10th of April 2018

Works are progressing well on site with the drainage and kerbing to the access roads leading to the Housing Association homes complete and ready for these to be tarred onĀ  the 12th and 13th of April.

 

Aerial Progress Photo of 6th April

 

Erection of the 20no homes for Highland Housing Association and Albyn Housing Society are progressing well with the structural kits to four of the six blocks substantially complete. Construction of the remaining two blocks will commence from the 16th of April. Roof tiling, windows & doors and internal works have commenced and are progressing well.

 

Structural Kit Erection at 28th March

 

Roof tiling works at 28th of March 2018